Search This Blog

Wednesday, September 12, 2012

General Dynamics NASSCO Completes First MLP Hull Ahead of Schedule

Mobile Landing Platform (MLP) |The shipbuilders of General Dynamics NASSCO have completed the structural assembly and weld-out of 26,241 metric tons of steel to erect the entire structure of the first Mobile Landing Platform (MLP) for the U.S. Navy.

Construction of the ship is progressing on schedule and under budget, with delivery scheduled for the second quarter of 2013.

The final block for the first MLP ship, comprised of the ship’s exhaust stacks and weighing 277 short tons, was lifted onboard via crane and installed on August 17.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.