SUBASE completes maintenance dredging days ahead of schedule


Naval Submarine Base New London
Naval Submarine Base New London (SUBASE) recently completed its scheduled comprehensive, maintenance dredging project, 11 days ahead of schedule and more than two million dollars under budget.

The project entailed removing more than 97,000 cubic yards of Thames River sediment from the areas around each of SUBASE's piers and quay walls.

Performed by Great Lakes Dredge and Dock, the effort brought down the berthing depth of the piers at SUBASE to the original design depth of 36 feet, plus two feet over-dredge.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.