After Gorshkov, another Navy project hit by delay

Free Image Hosting at www.ImageShack.usThe bad news for Navy shows no sign of stopping. The country's most ambitious ship-building project, construction of a 37,500-tonne indigenous aircraft carrier (IAC) at Cochin shipyard, is running way behind schedule.

Sources said current projections show IAC will be ready for delivery to Navy earliest by 2015, after completion of construction and trials, instead of the earlier date of 2011-2012.

The IAC project, cleared by the government in January 2003 at a cost of Rs 3,261 crore after several years of dilly-dallying, is lagging behind on "almost all fronts".

"First, there was a big problem in getting 20,000 tonnes of special quality steel for it till SAIL stepped in. Then, there was a huge delay in procurement of bulb bars. Once these was sorted out, other problems crept in," a source said.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.