As Gerald R. Ford nears delivery, two big hurdles remain

USS  Gerald R. Ford (CVN-78)The Navy's newest carrier is on track for its March 31, 2015, delivery. But significant hurdles remain with the ship's catapults and its arresting gear, which will receive intensive scrutiny and testing for the remainder of the year.

Construction of the first-of-class Gerald R. Ford is 89 percent complete, Rear Adm. Thomas Moore, program executive officer carriers, told reporters March 19.

Most of what remains is finish work. However, the test program is only 37.5 percent complete and, though on schedule, this will be the focus in the coming year.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.