Search This Blog

Tuesday, March 27, 2012

Boeing KC-46 tanker may be delayed -GAO report

[KC-767 (KC-46) Tanker Aircraft]One year into its development, the Air Force's new KC-46 refueling tanker being developed by Boeing Co faces "significant schedule risks" and technical challenges, and is already $900 million over budget, a congressional report found.

The Government Accountability Office, an investigative arm of Congress, said the Air Force had limited its liability for cost overruns on the $51.7 billion program by using a fixed-price contract, but schedule delays were still possible.

"Even with these safeguards, it is important to note that one year into development, Air Force and contractor development cost estimates exceed the development contract amount and significant schedule risks have been identified," GAO wrote in an annual report on the program required by Congress.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.