The latest schedule slip, now taking total KC-30 program delays to over two years beyond the original late 2008 first delivery schedule, is not believed to be of a technical nature, but is due to ongoing delays in writing the comprehensive technical documentation for the aircraft’s all-new boom and its remote operating station, which currently does not satisfy the RAAF’s stringent airworthiness standards.
The RAAF’s airworthiness requirements are recognised worldwide for their high standards, and without having the appropriate technical documentation upon which to establish an acceptable baseline, the RAAF is unable to verify the airworthiness of the boom and therefore clear it for operational use.