As development costs have risen to at least $3.9 billion, the scheduled dates to begin production and then deployment of the Triton drone have each slipped by more than two years, according to a Senate committee.
The Senate Appropriations Committee said in its report on funding defense programs in fiscal 2015 that it “is concerned with the cost and schedule breaches over the past few years” and is “troubled by software development delays” for the 70-aircraft, $15.3 billion program.