Cost of Nato's new HQ soars by 25 per cent

The new NATO headquartersThe construction costs for a new Nato headquarters in Brussels could soar by as much as 25 per cent presenting a bill to the British taxpayer of over £150 million at a time of national defence cuts.

The construction consortium building a state-of-the-art HQ for the Western Alliance has run into financial difficulties that could push the bill for the building up to a total of over €1.25 billion (£1bn).

Officials have confirmed "that the general construction contractor submitted a claim for extra costs and time to finalise the new Nato headquarters building, beyond their initial bid".

Read more

1 comment:

  1. So? The contractor bid it. To keep it, they need to honor that bid amount, otherwise, let's go to the next bidder.

    ReplyDelete

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.