The report said Boeing overestimated how many new parts it would need to build the 181 CH-47F Chinook helicopters under the five-year contract, and then installed largely used parts, resulting in overcharges of $7.4 million to $16.6 million.
The inspector general's report faulted the Army for not overseeing the contract properly, and noted it lacked a process to doublecheck Boeing's estimates and track the number of used or new parts that were actually installed.