The cost of developing the Kaveri was revised to Indian rupees (Rs) 28.39 billion ($560 million) in 2009, up from the original estimate of Rs3.83 billion allocated to the project in 1996, says Indian minister of defence A K Antony in a written reply to a question in parliament.
Costs involving the Tejas Mk II have nearly doubled to Rs57.77 billion from an expected Rs33.02 billion, while costs involving the naval Tejas have risen to Rs17.5 billion from Rs9.48 billion.