Structural Work on Gerald R. Ford Aircraft Carrier Reaches Halfway Point

Gerald R. Ford (CVN 78)Huntington Ingalls Industries, Inc. announced today that the structural production of the aircraft carrier Gerald R. Ford (CVN 78) has reached 50 percent completion.

The lead ship in the new class of carriers has been under construction at the company's Newport News Shipbuilding division since November 2009. It is on track to meet its scheduled launch in 2013 and delivery to the U.S. Navy in 2015.

Gerald R. Ford is being built using modular construction, a process where smaller sections of the ship are welded together to form large structural units, outfitting is installed, and the large units are lifted into the dry dock. Of the 500 total structural lifts needed to complete the ship, 250 have been accomplished.

Read more

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Fair Use Notice

This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner.

The material is being made available in an effort to advance understanding arms trade activities, for non-profit research and educational purposes only.

I believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law.

If you wish to use this copyrighted material for purposes of your own that go beyond 'fair use,' you must obtain permission from the copyright owner.

This is a completely non-commercial site for private personal use. No fee is charged, and no money is made off of the operation of this site.